Creekstone Farms – Arkansas City, KS

Following a fire at their meat production plant in Arkansas City, KS, Creekstone Farms wanted to do everything they could do to get their business back to full production as quickly as possible.

A previous relationship between Tippmann Group and key members of the Creekstone management team led Creekstone to look to Tippmann for help in getting their plant back up to speed.

Tippmann Group excels at fast-track design/build construction projects, and that reputation helped finalize Creekstone’s decision to choose Tippmann for the project. Tippmann also assisted in negotiating the loss value after the fire and worked with the insurance company to help expedite the project.

The building features a state-of-the-art plant-attached fab floor and was completed just 8 1/2 months after the day the engineering agreement was signed, and once the precast concrete was delivered, it took only 179 days to complete the project.

Facility Highlights:

  • 72,000 square foot Fab Floor expansion
  • Engineering agreement to completion – 257 days
  • Precast delivery to completion – 179 days