In February 1998 a fire destroyed one of Roundy's distribution facilities in Evansville, Indiana. Roundy's acted quickly to meet immediate demands, but needed a plan to ensure ongoing distribution requirements were met. They called Tippmann Group to discuss a new warehousing facility.

Tippmann designed a new state-of-the-art freezer/cooler distribution facility and broke ground in mid-August 1998. Ninety days later, Tippmann had the new 140,000-square-foot facility ready to accept product.

 

 

  • 140,000 square foot distribution facility
  • Ready to accept product 90 days after ground breaking
 
 